Street resurfacing begins in Menlo Park this week

by Contributed Content on July 20, 2025

Teichert Construction is beginning work on the 2025 Street Resurfacing project as part of the City of Menlo Park’s five-year street maintenance program to keep public streets in good condition.

Here is the schedule of surfacing that will take place this coming week.

Monday, July 21 – Tuesday, July 22
Woodland Avenue: Middlefield Road to Lexington Drive
Woodland Avenue: Pope Street to Woodland Avenue

Saturday, July 26
Middlefield Road: ​Willow Road to Santa Margarita Drive.

Message boards and public notices will be posted along Middlefield Road and impacted businesses and residents will receive a notice in advance of construction.

Additional information, including a map of the proposed resurfacing locations, is included on the project webpage.

Photo courtesy of City of Menlo Park

One Comment

Willows neighborhood July 22, 2025 at 6:35 am

Would like see pedestrian, bicycle, and micro-mobility infrastructure equal to what there is for cars if not greater, with the ever increasing traffic and lack of parking. More specifically parts of Woodland ave doesn’t have a sidewalk even though there was a study 20yrs and city code to install sidewalks when houses get new builds or some remodels.

Comments are closed.

Upcoming Events
HELP SUPPORT INMENLO!

Please help support InMenlo! Your contribution will help us continue to bring InMenlo to you. Click on the button below to contribute!