Updated timeline for applicant’s lawsuit regarding 80 Willow Road builder’s remedy project

by Linda Hubbard on November 1, 2026

proposed Willow Park development

Menlo Park Mayor Betsy Nash reports:

For those following the 80 Willow Road builder’s remedy project, the timeline of the applicant’s lawsuit has changed.  Here’s the current schedule (dates may change):

  • Nov. 18: The developer files its main written argument
  • Dec. 1: The City files its written response
  • Dec. 8: The developer files its final reply
  • Dec. 14: Court hearing
  • Mid to late January 2027: The judge is expected to issue a decision

Pictured is Willow Park aerial view, rendering by Solomon Cordwell Buenz